The Italian Property Buying Timeline: From Proposta to Rogito, Step by Step (2026)
By Patrick · 2026-07-15
Foreign buyers often assume that once an offer is accepted, the deal is essentially done. In Italy, that's when the real process begins. A straightforward cash purchase often takes one to two months from accepted offer to deed. Add a mortgage, agricultural land or a planning problem to fix, and it can take three months or more. This guide walks through the three legal stages, proposta, compromesso and rogito, so you know what happens next and where deals typically slow down.
The three-stage process, at a glance
An Italian residential purchase moves through three legal steps, each with its own paperwork:
- Proposta d'acquisto (purchase proposal): your formal written offer, usually with a small deposit.
- Compromesso (contratto preliminare, or preliminary contract): the binding contract, usually with a larger deposit, registered with the tax office.
- Rogito (rogito notarile, or notarial deed): the final signing in front of a notaio (notary) that transfers ownership.
Sometimes the stages merge: an accepted proposta can itself be the preliminary contract, and some buyers go straight to the deed.
Stage 1 — Proposta d'acquisto: making the offer official
The proposta is your written offer for a specific price, a deadline for the seller's answer and any conditions, for example that you get a mortgage. It is usually accompanied by a deposit, often a cheque made out to the seller that the agent holds until the seller answers.
Read it as a contract, because it can become one. Once the seller accepts it, the accepted proposta can already count as the preliminary contract, with all the clauses printed on the agency's form, according to the Italian notaries' guide to the preliminary contract. So any condition you need, such as "subject to mortgage approval" with a deadline and a full refund if the loan is refused, belongs in the proposta itself. Without it, a refused loan does not release you.
Stage 2 — Compromesso: the deposit, the checks and the registration
The compromesso sets out the price, the payment schedule, the date of the deed and the conditions. It usually comes with a larger deposit, often paid as a caparra confirmatoria. That kind of deposit cuts both ways: if you withdraw without a valid reason, the seller keeps it; if the seller withdraws, you can withdraw too and claim double (art. 1385 of the Civil Code). The amount is negotiated; there is no legal standard.
This is the stage for the checks, and they should start before you sign, not after:
- Planning and building compliance. A geometra (surveyor) compares the house with its permits and the cadastral plan, and flags any abuso edilizio (unpermitted work). The notaio checks that the deed cites a valid permit, not that the house matches it; our guide to planning compliance explains why.
- The contract itself. An independent lawyer (avvocato) who reviews the compromesso before you sign is standard practice for foreign buyers, because the notaio is a neutral public official who does not represent you in the negotiation.
- Agricultural land. If the house comes with farmland, check whether a farmer has a right of first refusal; see our guide to prelazione agraria.
Registration is compulsory. The compromesso must be registered with the Agenzia delle Entrate within 20 days of signing, with a fixed tax of €200 plus 0.5% of the caparra (Agenzia delle Entrate). Registration does not protect your deposit against a later sale or the seller's creditors. That protection comes from transcribing the contract in the property registers (trascrizione), which requires the contract to be signed before a notary. It costs more, and it is worth considering when the deposit is large or the deed is months away.
The agency commission is usually due once the preliminary contract is signed, not at completion, a detail that surprises many foreign buyers.
If you are financing the purchase, apply for the mortgage now and run it in parallel with the checks. The Italian notaries' guide says that, as a rule, 60 days from application to signing can be more than enough, but a late application is one of the most common reasons a deed is postponed.
Stage 3 — Rogito: the final deed
The rogito notarile is the final signing in front of the notaio that transfers ownership. A few things foreign buyers don't expect:
- The deed is in Italian. If you don't understand Italian, it is signed with a sworn interpreter of your choice, who also writes a translation into your language next to the Italian text (art. 55 of the notarial law). Arrange it with the notaio well in advance.
- Payment must be traceable. The deed states how the price was paid, usually by bank transfer or banker's draft. Allow time for an international transfer to arrive.
- You can ask the notaio to hold the money. At the request of either party, the notaio must keep the price on a dedicated account and release it to the seller only once the deed is registered and transcribed (L. 147/2013, art. 1 c. 63). It protects you against a mortgage or seizure registered against the house at the last minute.
- You own the house when the deed is signed, but the notaio still has to register and transcribe it in the public property registers afterwards.
- If you can't attend in person, a procura (power of attorney) signed abroad must be notarised and carry an apostille, and usually needs a translation. Arrange it early, not in the last week.
The deed is also when most of Italy's purchase taxes and fees are paid: roughly 7% to 17% of the price, depending on the tax base and your buyer status. Our guide to the real cost of buying a house in Italy itemizes every one of them.
What actually delays a purchase
- Mortgage approval, especially with income earned outside Italy.
- A codice fiscale obtained late. You need this Italian tax code before you can sign anything. It is free from the Agenzia delle Entrate or an Italian consulate; get it before you make an offer.
- Prelazione agraria. For agricultural land, a qualifying tenant farmer or neighbouring farmer must be offered the sale first and has 30 days to decide.
- Planning or title problems found during the checks, which the seller may have to regularise before the deed.
- Paperwork from abroad: power of attorney, translations and the interpreter.
An illustrative timeline
Every purchase is different; this is a typical shape for a purchase with a mortgage:
- Week 0: proposta accepted, with any conditions written into it.
- Weeks 1–3: compromesso signed and registered within 20 days; deposit paid; agency commission usually due; mortgage application submitted.
- Weeks 2–8: checks (geometra, lawyer) and the bank's valuation and approval run in parallel.
- Weeks 8–10: funds arranged; rogito signed; keys handed over.
A cash purchase with clean papers can be quicker. Rural land with pre-emption rights, a planning problem or cross-border financing can stretch it. Building that buffer in up front is far less stressful than discovering it mid-purchase.
Know exactly where you are in the process
Every Trovara property report includes a Due Diligence Checklist phased across these stages — pre-offer, contract, pre-closing and post-purchase — alongside eight further pillars covering legal risk, structural condition, financing costs and market value for the specific property you're considering. You can see the format in our sample report.
This guide was prepared with AI assistance and reviewed by the Trovara team. It describes the standard Italian purchase process as of 2026, based on the Civil Code, the notarial law, the Agenzia delle Entrate and the Italian notaries' guides, checked in October 2026; timelines are illustrative. This is not tax or legal advice. Always verify your specific timeline and obligations with a notaio, a lawyer or a commercialista before signing.
Photo credits: cover — "Signature Contract Close Up Tool Edited 2020" by Tool Dude8mm (mechanicalcaveman.com), CC BY 2.0, via Flickr.
Frequently asked questions
How long does it take to buy a house in Italy?
A straightforward cash purchase often takes one to two months from accepted offer to deed. With a mortgage, agricultural land or a planning problem to fix, allow three months or more. The Italian notaries' guide says that, as a rule, 60 days from mortgage application to signing can be more than enough.
Is an accepted proposta binding in Italy?
Yes. Once the seller accepts your written offer, it can already count as the preliminary contract, with its printed clauses. Put any condition you need, such as getting a mortgage, into the proposta itself, not only into the later compromesso.
What is a caparra confirmatoria?
A deposit paid when the preliminary contract is signed. If the buyer walks away without a valid reason, the seller keeps it; if the seller walks away, the buyer can withdraw and claim double (art. 1385 of the Civil Code).
Does the preliminary contract have to be registered?
Yes, within 20 days of signing, with a fixed tax of €200 plus 0.5% of the caparra. Registration does not protect the buyer against a later sale or the seller's creditors; that needs the contract transcribed in the property registers, which requires a notary.